Temple Quarter sits at the heart of Bristol, one of the UK’s most productive and fast-growing regions and a focal point for the West of England’s £39bn economy. Temple Quarter will transform over 130 hectares of brownfield land over the next 25 years into a series of thriving, well-connected mixed-use communities. The regeneration of the area will deliver 10,000 new homes in a mix of types and tenures, including much-needed new affordable homes. 22,000 new jobs will be created, bringing inclusive economic growth to the city and new opportunities for Bristol’s citizens, alongside £1.6bn annual income to the city economy.
The Temple Island Project forms part of the Bristol Temple Quarter Regeneration Project.
Proposals for Temple Island are for a mixed-use scheme that could bring new homes, offices, and commercial space to the area, as well as a new hotel and conference facility. In the north of the site, new student accommodation linked to the University of Bristol’s new Enterprise Campus is proposed. The Council is bringing this derelict brownfield land back to life, creating a vibrant place to spend time in the day and evening.
As part of these plans, Bristol City Council (BCC) has submitted a planning application to enable the future development of the Temple Island site. The planning application seeks consent for engineering works that will prepare the Temple Island site for future development.
The works will comprise the following:
Initial Budget set at 14.5 million.
To ensure BCC followed a compliant route to market, a thorough search was undertaken to establish whether there were any suitable internal Council or National Frameworks which could deliver the Scope of Works in a cost-effective and timely manner. This proved fruitless and the Project Team, with assistance from V4, decided to use the Open Market Procedure, as this approach:
V4 managed the Early Market Engagement process with interested suppliers and the Project Team.A workshop was convened where suppliers could input into the procurement approach with regards to the Scope, Terms and Conditions of Contract, Timescales, and how to achieve better value for money. The outcome of the workshop were proposals which the project team could review and consider further and incorporate these where required into the Scope, Contract and Procurement process.
V4 Managed this process:
Resulted in 12 tenders.
V4 were responsible for the following:
Scoring the Mandatory
selection Questionnaire with PM.
Managing the process with
Consequently 8 remaining suppliers were evaluated against the stage 2 Award criteria.
Tender clarifications were
managed and responses co-ordinated with the evaluation team.
Undertook the complete commercial evaluation of the Activity Schedule to ensure that the Prices received were compliant, accurate and that there were no erroneous rates.
This required in depth knowledge of Construction and Estimation of Contract
The biggest challenge was that Suppliers complied with the Scope of Works, especially the Ground Remediation Performance Specification and to ensure that the Prices submitted were complete and fully aligned with the Activity Schedule.
Managing the scoring with the internal and external consultants to ensure fairness and to reduce the risk
Chairing and concluding the
Finalising contract terms with
Reviewed and checked the
Compiled the scoring, issued
Issued the award letters
The difference in scoring for the top 3 suppliers was marginal. Therefore, the suppliers were managed during the Standstill period which did not lead to challenge.
The ITT and the Proposals were issued to legal for: Award notices and Precontract were managed to ensure that this was then pushed to Proactis where the contract was managed.
The contract was let at £4.6 million which was some 2 million below the Quantity Surveyor’s project estimate and nearly £8 million below the Budget the Council set aside to deliver the project.
The programme was maintained, and the works are due to start as per programme on 2nd January 2024.